Springfield New-Build Timeline: From Lot to Keys

January 1, 2026

Building a home in Springfield should feel exciting, not overwhelming. You want a clear path from picking the lot to getting the keys so your family can plan school, work, and moving day with confidence. This guide gives you a realistic timeline, key checkpoints, and local factors that can affect your schedule in Sarpy County. You will know what happens when, who does it, and how to keep things moving. Let’s dive in.

Springfield timeline at a glance

For a semi-custom home on a prepared lot, a typical timeline in Sarpy County is 6 to 9 months from lot purchase to keys. A fully custom home or a site that needs extensive work often takes 8 to 14 months or more. The big milestone groups are: lot due diligence, contract and financing, design and selections, permitting and site prep, foundation, framing, mechanicals, insulation and drywall, interior finishes, final inspections, Certificate of Occupancy, and closing.

Two planning tips matter most:

  • Build in a 4 to 8 week buffer beyond the builder’s estimate. Weather, inspections, and punch list items can add time.
  • Make high-impact selections early, like cabinets, windows, and appliances, so long-lead materials do not slow your schedule.

Phase-by-phase timeline

A. Lot due diligence and purchase (2 to 6 weeks)

You confirm the lot is a good fit and clear of surprises. Typical steps include a survey, title work, HOA covenants, and checking setbacks and easements. If the lot is not on public utilities, plan for soil and perc testing to confirm septic feasibility.

Key notes:

  • Documents: title report, plat, survey, recorded covenants, and county lot data.
  • Watch for delays from title issues, survey scheduling, or a failed perc test.

B. Builder contract and design (2 to 8 weeks)

You sign a construction contract and finalize plans, elevations, and structural details. You also set allowances and a selections schedule. Semi-custom designs typically move faster than full custom plans.

What to lock in now:

  • Layout changes and structural upgrades.
  • Exterior materials and major interior finish levels.
  • Clear change-order rules, warranty terms, milestone payments, and a target completion window.

C. Financing approval and loan closing (3 to 6 weeks)

You secure a construction or construction-to-permanent loan. Lenders generally need a full plan set, specs, and a budget for appraisal and underwriting. Closing on the loan kicks off initial funding.

Expect:

  • Underwriting and appraisal once plans are complete.
  • An initial draw or builder deposit at closing.
  • Faster timelines if you are preapproved and your lender handles construction loans often.

D. Permitting and utilities (2 to 8+ weeks)

You or your builder submit for building permits with the Village of Springfield or Sarpy County, depending on location. If you need a septic system or well, permits and reviews can add time. Utility coordination for electric, gas, water, and sewer starts now.

Plan for:

  • A complete permit package and code compliance checks.
  • Driveway or culvert approvals where required.
  • Longer timelines for rural lots and any off-site utility extensions.

E. Site prep and foundation (2 to 6 weeks)

The site is cleared and graded, erosion control is installed, and the building pad is set. Excavation, footings, and the foundation are formed and poured, then backfilled after curing. Inspections happen before concrete and at the foundation stage.

Weather watch:

  • Cold temperatures and wet ground can delay pours.
  • Footings must be below frost depth, which affects timing in winter.

F. Framing and exterior envelope (3 to 6 weeks)

Walls go up, roof trusses set, sheathing added, and windows and doors installed. The roof is dried in and exterior wrap and siding begin. A framing inspection is completed before insulation.

Keep momentum by:

  • Confirming window and door orders early.
  • Walking the framed home to verify outlet, window, and door placements before rough-ins.

G. Mechanical, electrical, plumbing rough-ins (2 to 6 weeks)

HVAC ducts and equipment are installed, plumbing supply and drains are run, and electrical wiring is pulled. Separate rough inspections are scheduled for each trade.

Stay organized:

  • Finalize outlet locations, lighting, and plumbing fixture choices.
  • If you change a wall or layout now, it can cascade into rework and delays.

H. Insulation and drywall (2 to 5 weeks)

Insulation is placed and inspected where required. Drywall is hung, taped, and prepped for paint. Interior priming often wraps this stage.

What helps:

  • Confirm any sound-deadening or upgrade insulation choices in advance.
  • Keep site access clear so trades can work in order.

I. Interior finishes and systems (4 to 12 weeks)

Interior finishes bring the home to life. This includes paint, trim, cabinetry, countertops, tile, flooring, and final electrical and plumbing fixtures. HVAC systems are started up and balanced, and appliances are installed near the end.

Lead time alert:

  • Cabinets, custom windows, specialty doors, and some appliances can take weeks to months.
  • Lock selections early and order as soon as plans finalize to avoid idle time.

J. Final inspections, CO, and closing (1 to 4 weeks)

Your builder schedules the final building inspection. Once you receive the Certificate of Occupancy, you complete your final walkthrough and punch list. Your lender processes the final draw and converts the loan to a permanent mortgage if you used a single-close product.

Before move-in:

  • Get the CO first and confirm utilities are active.
  • Request final lien waivers, as-built drawings, manuals, and warranty contacts.

Financing checkpoints and timing

Choosing the right loan can simplify your timeline. A construction-to-permanent loan uses a single closing, funds the build, and converts to a mortgage at completion. A construction-only loan requires a second closing later. Some builders offer builder-financed options, but make sure you understand the true costs.

Expect these milestones:

  • Preapproval and early document collection.
  • Underwriting and appraisal once plans and specs are ready.
  • Draws tied to specific stages like footing, framing, rough-ins, drywall, finishes, and final.
  • Interest-only payments during construction, then conversion to your mortgage.

Helpful timing ranges:

  • Underwriting and appraisal typically take 3 to 6 weeks when paperwork is complete.
  • Draw approvals often need 48 to 72 hours after the request. Third-party inspections can add a few days.
  • Budget 1 to 3 weeks to clear final lender conditions before conversion or closing.

Pro tips:

  • Work with a lender experienced in construction loans in Sarpy County.
  • Clarify who orders draw inspections and how lien waivers are handled.
  • Set aside a 5 to 10 percent contingency for changes or site surprises.

Local rules and site factors to confirm

Springfield projects can fall under Village of Springfield or Sarpy County review. Confirm your permit authority based on the parcel location. Ask for current processing times, inspection scheduling windows, and any local code amendments.

Key local checks:

  • Septic and well: If you are not on public utilities, plan for perc tests, soil reports, and permit reviews. Rules cover system type and setbacks.
  • Floodplain: Check FEMA mapping for any flood zone considerations. A regulated floodplain may require an elevation certificate and engineering.
  • Driveway and erosion control: Driveway permits, culverts, and stormwater measures are common requirements during grading.
  • Utilities: Identify providers early. Off-site service extensions can add cost and time.
  • HOA or architectural review: Many boards take 2 to 4 weeks or more to review exterior materials, colors, and landscaping.
  • Climate: Nebraska winters bring freeze and thaw cycles. Foundation work must account for frost depth and weather windows.

Common delays and how to avoid them

The most frequent slowdowns are weather, permit or inspection backlogs, long lead materials, and change orders. Site surprises like poor soils or high groundwater can also add time and cost.

How to stay on track:

  • Add a 4 to 8 week buffer to your move date.
  • Finalize cabinets, windows, doors, appliances, and exterior materials as soon as plans are set.
  • Be decisive with layout and fixture locations before rough-ins.
  • Schedule utility meters and connections in advance of final inspection.
  • Keep your paperwork organized, including plans, permits, draw requests, and lien waivers.

Your planning checklist

Pre-construction:

  • Get lender preapproval and gather income and asset docs.
  • Order survey, review title and covenants, and confirm setbacks and easements.
  • Verify utility availability or plan for septic and well feasibility.

During construction:

  • Track selection deadlines in a shared calendar.
  • Confirm draw schedule, inspection timing, and documentation needs.
  • Visit the site at key checkpoints and keep communication open with your builder.

Four to six weeks before target move:

  • Confirm the CO process and expected inspection dates.
  • Lock mortgage terms and prepare for conversion or closing.
  • Schedule movers, set up utilities, and plan temporary housing if needed.

Closing week:

  • Do the final walkthrough and create a punch list.
  • Collect final lien waivers and warranty packets.
  • Verify utility activation, confirm keys and access codes.

Example timelines

Semi-custom, prepared lot on public utilities:

  • Lot to CO in about 6 to 9 months if permits, inspections, and materials flow on schedule.
  • Add 4 to 8 weeks as a buffer for punch list and final approvals.

Custom build with septic and more site work:

  • Lot to CO in about 8 to 14+ months, depending on design complexity, permit reviews, and specialty materials.
  • Plan for a longer selections phase and early orders for custom items.

Selections and orders that matter most

Some choices drive your schedule more than others. Prioritize these early:

  • Cabinets and countertops.
  • Windows, exterior doors, and garage doors.
  • HVAC equipment models and electrical fixtures.
  • Appliances, especially specialty or high-demand models.

Locking these items early reduces idle time and keeps trades moving.

Partnering with your agent and builder

Clear plans, early selections, and steady communication make the biggest difference. You want a builder that shares schedules, orders long-lead items early, and is proactive with inspections and lender draws. You also want an advocate who understands lots, utilities, and builder contracts so you do not miss a step.

If you are looking in Springfield or greater Sarpy County, you can partner with a local, construction-savvy agent who guides lot selection, builder negotiations, and new-build timelines from start to finish. When you are ready, reach out to Missy Ruff for hands-on help coordinating your Springfield build.

FAQs

How long does a semi-custom new build take in Springfield, NE?

  • Most semi-custom projects take about 6 to 9 months from lot purchase to keys, plus a 4 to 8 week buffer for punch list and approvals.

What inspections happen during construction in Sarpy County?

  • Common checkpoints include footing and foundation, framing, separate rough-ins for mechanical, electrical, and plumbing, insulation, and a final inspection for the Certificate of Occupancy.

Do I need a construction-to-permanent loan for a new build?

  • You can choose construction-to-permanent for a single close, construction-only with a second close, or builder-financed options; confirm timelines, draw rules, and true costs with your lender and builder.

How does Nebraska winter affect foundation work and schedule?

  • Freeze and thaw cycles can delay excavation and concrete pours; footings must be below frost depth, so plan foundation work for favorable weather when possible.

When should I schedule movers for a new build in Springfield?

  • Schedule movers only after you receive the Certificate of Occupancy and utilities are active, and keep a 4 to 8 week buffer beyond the builder’s target date.